14.04-25.04.2025 and update

 Update: 

We finished the maintenance of 2 openings

We continued piping work (plumbing)

We digged a bit more the level of ground floor north house (we needed the permission of the structural engineer to do that)

We did some preparation work for the rest of the plumbing works. 

**Unfortunately, we had to remove two plants (one is a rose plant) in front of the bathroom ground floor north house because some pipes of the bathroom will be placed and be hidden there. I am generally against destroying existing planting but that was unfortunately inevitable. I will personally replant two plants once the works are done (smiley)


As I have already written to you, the work slowed down tha last period because we were waiting for the structural engineer's visit and his survey. I was afraid that his proposal - especially the idea of underpinning the south house would interrupt/cause damage to other works.

Finally, following his visit to the building, our structural engineer informed us that the south house's underpinning is not necessary. To ensure the building’s stability, given the absence of foundations, it is sufficient to extend the existing stone ledge from the narrow side of the building along the longer side, up to the door before the shower. Naturally, this construction will include a framework that will be securely connected to the main structure. That is indeed great news because the cost of the underpinning would be highten.


We are currently awaiting his detailed structural study in order to proceed with the construction. Similarly, we are also waiting for his detailed study regarding the reinforcement works for the northern old building.


For this week we have planned to work on

electrical installations

continue parts of plumbing installations

I have also arranged an appointment with an internet technician in order to specify the position of the starling equipment and coordinate with the rest of the electrical works.