26.02.2025

Image
 Wall and opening

21.02.2025 and update

Image
 Unpdate We almost finished the excavation works yard. We placed new timber beams on the floor structure of south house and covered the hole of the staircase. We did supporting work for the small part of the fallen wall of south house. The wall will be filled now with stones this week.

15.02.2025 and update

Image
  We finished the excavation of the external shower yard we excavated the yard and the location of the external kitchen we continued the reformation of openings of the south house For this week 17-21.02.2025 we have planned to  finish the formation of the yard  continue reforming of the openings south house Reforming of openings Yard excavations

11.02.2024

Image
 Reforming of openings Yard excavations

07.02.2025 and update

Image
The weather was good so the works of external demolitions started. We -excavated the part of the external shower and the middle yard. For this week, 10-14.02.2025 we have planned to start reforming the openings of the south house.

05.02.2025

Image
External immediate landscape excavations