26.05.2025

Image
Plumbing

16.05.2025

Image
 Replacement of damaged wooden beams

13.05.2025

Image
 Connectios north house Replacement of damaged lime stones south house (last opening)

12.05.2025

Image
 More electrical installations on the walls/ceiling south house

07.05.2025

Image
 Drainage south 1st floor infills

06.05.2025

Image
 Electrical installation south 

05.05.2025

Image
 Metal Waterproof tray for bathroom south house

02.05.2025 and update

Image
Here is the news from the construction site for last week 28.04-02.05.2025 We started the electrical installations of south house We continued the plumbing installations parts of both houses