27.02.2026

Image
 Excavation for drainage/new staircase south house south facade Staircase/ stone wall next to the storage room finished Windows/doors south house

25.02.2026

Image
 Ligaria north Drainage south and stonework of the waterproofed part

24.02.2026

Image
 

18.02.2026

Image
 Internal pointing bedroom north house

16.02.2025

Image
 Stonework steps next to north house

13./2.2026

Image
 Ceiling south house ligaria 1st layer finished

12.02.2026

Image
 

10.02.2026

Image
Painting the edges necessary for the ligaria installation Reinforced plastering Repairing on the walls bedroom north house and start of internal pointing Storage room cleaned and painted - pvs machines will be installed on the back side  wall 

09.02.2026

Image
 North house external pointing finished! Steel balcony south house Water proofing south house (1st hand)