Update: We finished the maintenance of 2 openings We continued piping work (plumbing) We digged a bit more the level of ground floor north house (we needed the permission of the structural engineer to do that) We did some preparation work for the rest of the plumbing works. **Unfortunately, we had to remove two plants (one is a rose plant) in front of the bathroom ground floor north house because some pipes of the bathroom will be placed and be hidden there. I am generally against destroying existing planting but that was unfortunately inevitable. I will personally replant two plants once the works are done (smiley) As I have already written to you, the work slowed down tha last period because we were waiting for the structural engineer's visit and his survey. I was afraid that his proposal - especially the idea of underpinning the south house would interrupt/cause damage to other works. Finally, following his visit to the building, our structural engineer informed us...