Posts

Showing posts from March, 2025

26.03.2025

Image
 Drainage water proofing layer (1st hand ,2 more pending)

22.03.2025

Image
 Drainage concrete work

14.03.2025

Image
 The other rock Pointing samples,the design team prefer the one below

12.03.2025

Image
 Excavation for drainage south house Cleaning the rock 

01.03.2025 and update

Image
  Here is the news from the construction site for the past week. We filled the fallen wall part We are close to finishing the reforming of openings of the south house. For this week 04.03.2025-07.03.2025 We have planned to  finish the reforming of openings of the south house replace the damaged lime stones of existing openings of south house