17.01.2025 and update

 Previous week (13.01.2025-17.01.2025) we

removed the suspended ceiling of ground floor south house
removed tiles and cement layer of ground floor north house- that will permit us to have a heighten space (new bathroom)
started removing the external existing pointing
made trials of cleaning the color of the stones (1st floor south house)

For the week (20.01.2025-24.01.2024) and the the upcoming weeks we have planned
 to focus on the external wall works on the south house - reforming openings and removal of existing pointing.
We also have planned to start the demolishing of the immediate landscape.








Comments

Popular posts from this blog