08.11.2024 and update
Previous week (06.11-08.11) we
1. prepared the internal of the house for the removal/demolishing works
2. removed the build in shelves/kitchen/cabinets/sanitare etc
3. started demolishing the internal walls and removing the plaster from the internal part of the stone walls.
Regarding the week (11.11-15/11) we will continue
the internal demolitions and removals.